Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Negative cost

1 reply [Last post]
Dylan Wan, PMP EVP
User offline. Last seen 10 years 5 weeks ago. Offline
Joined: 9 Mar 2005
Posts: 13
Groups: None
I found that you can enter a negative value in the baseline cost and all cost columns.

Do you ever use the negative cost value in Microsoft Project?

Replies

Chris Oggham
User offline. Last seen 10 years 5 weeks ago. Offline
Joined: 20 May 2004
Posts: 605
Groups: None
Dylan,

I don’t recall ever having needed to do this in MS Project, as by default Actual Costs are calculated by the software. However, you may be able to do what you want this way.

Click on the View menu and select Task Usage.
Click on the View menu again, point at Table and click on Cost.

Now click on the Format menu, click on Detail Styles and then select the Usage Details tab.
Hold down CTRL and in the Available Fields list, click on Actual Cost, Baseline Cost and Cost, then click Show, click OK.

Click on the Tools menu, select Options, click on the Calculation tab and uncheck the Actual Costs are always calculated by Microsoft Project check box, click OK.

You will now be able to enter Task Name, Fixed Cost, Actual Cost, and Baseline Cost all of the Cost fields will accept negative values.

Chris Oggham