Option ALAP in MSP is simmilar to ZFFC in P3 so valuable for You of course. But other interesting option is setting the finish date of project (instead of traditional start date project - in MSP we have only start OR only finish...). In this case MSP assume that all tasks are ALAP automatically. Meybe this way is valuable too. If You change finish date for start date you can revert (!) it for standard ASAP schedule. It is practical way in some cases, I suppose.
It may be used for the initial planning. But the schedule will change during project execution and these additional constraints being artificial will influence future schedules.
If you assign the task constraint ALAP then total slack as well as free float become zero, but if insert a column of free slack and then put another constraint FNET to make free slack zero.eg if task is showing 2 days free slack with current task finish date then you put FNET 2 days later then your free slack will become zero.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Option ALAP in MSP is simmilar to ZFFC in P3 so valuable for You of course. But other interesting option is setting the finish date of project (instead of traditional start date project - in MSP we have only start OR only finish...). In this case MSP assume that all tasks are ALAP automatically. Meybe this way is valuable too. If You change finish date for start date you can revert (!) it for standard ASAP schedule. It is practical way in some cases, I suppose.
Good Luck
It may be used for the initial planning. But the schedule will change during project execution and these additional constraints being artificial will influence future schedules.
If you assign the task constraint ALAP then total slack as well as free float become zero, but if insert a column of free slack and then put another constraint FNET to make free slack zero.eg if task is showing 2 days free slack with current task finish date then you put FNET 2 days later then your free slack will become zero.
As you have correctly alluded to setting a task in MSP to ALAP consumes all Total Float and not Free Float as in Primavera software.
I have not found a solution.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Book Publishers, Training & Consulting
www.eh.com.au