Days Due vs Days needed - what if you when you add up delays each month it is way more than needed?

1 reply [Last post]
John Reeves
User offline. Last seen 2 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Days Due vs Days needed - what if you when you add up delays each month it is way more than needed?  -  So do you have to give an extension for way more days than necessary just because there was fat in schedule, or they are able to condense the work?  If they will be done with a job in 20 days, do you have to give an extension for 60 days because that is what all of the delays added to? - obviously the "effect" was less than the raw numbers.

Replies

John Reeves
User offline. Last seen 2 weeks 3 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Another way to phrase this: you are delayed 60 calendar days, the work gets done and it turns out it only delayed the job 50 days?  Do you get a 60 or 50 day extension and why?