Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

"What if" contractor 6 months behind, then essential procurement item 9 months behind? construction acceleration?

No replies
John Reeves
User offline. Last seen 2 weeks 6 days ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

"What if" contractor 6 months behind, then essential procurement item becomes 9 months behind?  Is it unfair construction acceleration if the contractor is still pushed for overtime and accelleration even though there is a worse delay than the original - & that being a essential procurement item (like elec switch gear) that cannot be accellerated?  They are late, but they are also then  hurring just to wait...?  Is that unfair constructive accelleration - I am guess not but I do not know.  I assume the Owner goes after the GC for LD's and the GC goes after the supplier.

Patrick Weaver
User offline. Last seen 1 day 3 hours ago. Offline
Joined: 18 Jan 2001
Posts: 383
Groups: None

The answer to this question depends on who's responsible for the risk of each delay.  If the client has some responsibility for one of the delays your are looking at a concurrent delay situation, if the contractor is responsible for both, the contractor has a problem. 

Concurrent delays are a complex issue affected by the contract and by diffeent interpretations of law in various jurisdictions see: https://mosaicprojects.com.au/PMKI-ITC-020.php#Concurrent