Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Claim / EOT Management Requirement

22 replies [Last post]
Jithin Kambhikanam
User offline. Last seen 8 weeks 2 days ago. Offline

Hello Everyone,

Just a topic to know what will help Claim Management in a Project from which we (Contractor or Subcontractor) can calculate the delay charge.

In most of the Contract Client would have already mentioned the amount which will be charged per day for delay which would be a % of the Contract Value.

 

I have listed down few if those are not relavant please let us know.

Baseline Schedule

Manpower Schedule

Equipment Schedule

Letters regarding the cause of delay.

 

Thanks

Jithin

Replies

Jithin Kambhikanam
User offline. Last seen 8 weeks 2 days ago. Offline

Thanks Mike. Got your Point. So either the Contract should say that "During prolongation Unit Rate can be used" or to show the Client the Account System of the Project.

Thanks

Jithin

Mike Testro
User offline. Last seen 35 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Jithin

If your contract says that as an EPC contractor you can used the scheduled rates for prolongation costs then that is what you do.

If not then you have to substantiate the actual costs.

As I have said before in this discussion you can show your accounts to the client or employ a registered accountant or independant QS to certify that the costs that you have listed are correct.

Best regards

Mike Testro

Jithin Kambhikanam
User offline. Last seen 8 weeks 2 days ago. Offline

Thanks Mike and Raymund,

What is an Audited Cost and who would come and measure it . What all would be included in Audited Cost.

In UAE the the EPC Contracts (Oil and Gas) are on Lumpsum basis in which you award the Contract to a EPC Contractor to do a certian work say 30 Million $.

So when the EPC Contractor has worn the bid for 30 Million $ he wold have included the cost for Manpower + Equipment + Insurance + Tax + Profit + Overhead (Overhead in the sense that a % of Running cost of Head Office of the company for 12 Months which will include the cost of people who would be working for mutiple project at the same time ) for the total duration of Project say 12 Months.

With the Contract we do give a Manpower and Equipment Schedule with which they can calculate the manpower and equipment alloted for the Project. So even if we flood the Project with other manpower which was not mentioned in the schedule that wont be paid for.

So how owuld Auding Help us in getting the Cost for EOT.Would the Profit be included in that ?

Regards

Jithin

Raymund de Laza
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Jithin,

As Mike said, it must be the audited Cost in a span of the Original Project Duration.

Mike Testro
User offline. Last seen 35 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Jithin

That is why it has to be audited costs. Another trick contractors play is to flood the site with un necessary staff from another project which they have delayed. Its a rough old world out there.

Jithin Kambhikanam
User offline. Last seen 8 weeks 2 days ago. Offline

Raymund,

OK so after the approval of time we can claim for the exepense for the EOT Claim by Days. 

So shouldnt we include in the Contract the unit rate for all the item ( Manpower , Equipment , Insurance, Running Cost, Bank Charge ) which is signed both parties the unit rate for everything example,

 

Project Manager  - 500 $ / Day

Project Engineer - 370 $ / Day

Crane 25 Ton - 317 $ / Day

 

If this is not included in the Contract wouldnt there be a Problem during expense claim for EOT as the Client might not agree to the unit rate we (Contractor) have put in the expense claim ( Might say we have charged high).

Warm Regards

Jithin

 

 

Raymund de Laza
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Jithin,

Contractor has the right to claim for compensation from the Extension of Time resulted from Non Excusable Client Cause-Delays.

The Extended Overhead (Daily Rate) shall be determined and shall be multiplied with the agreed number of days of Extension.

 

Jithin Kambhikanam
User offline. Last seen 8 weeks 2 days ago. Offline

Thanks Raymond. So overhead charges are non excusable for EOT so it will be paid.

Raymund de Laza
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Hi Jithin,

In my understanding from your Post, Contractor Calculation of delay compensation. This is also termed as the Extended Overhead.

A proven non-excusable client delays are compensable delays with Extended Overhead.

Jithin Kambhikanam
User offline. Last seen 8 weeks 2 days ago. Offline

Thanks Mike. Ya u were right i was confused . Now got the clear point. 

So,

LAD - Put by Client/Employer

EOT - Requested by Contractor

 

Warm Regards

Jithin

Mike Testro
User offline. Last seen 35 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Jithin

You are confusing LAD's - Damages with Prolongation costs.

The first task of a contrators EoT claim is to avoid LAD's - the second part is to establish an entitlement to recovery for prolongation cost /loss and expense.

The two procedures are seperate and require different approaches - this is true for every form of contract that I have encountered.

Best regards

Mike Testro

Jithin Kambhikanam
User offline. Last seen 8 weeks 2 days ago. Offline

Hi Mike,

But most of the Contracts are written on the Clients favour in which it says what will happen when the delay is by the Contractor like " Per day of delay is 0.10% of Contract Value (Lump Sum Contract) to a maximum of 10% ". No clasue states as how to calculate the delay cost if the delay is by Client. Then what do we do.

Thanks

Jithin

Mike Testro
User offline. Last seen 35 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Jithin

Everything depends on what the contract says - a delay analyst has to read the contract before doing anything else.

Remember that contractor concurrent delays will restrict the prolongation recovery.

Best regards

Mike Testro

Jithin Kambhikanam
User offline. Last seen 8 weeks 2 days ago. Offline

Thanks Mike,

That helped a lot. So the Cost of Delay (If the delay is caused by Client) is to be mentioned in the Contract. On the basis of this the delay cost calculation would be done.

Regards

Jithin

Mike Testro
User offline. Last seen 35 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Anthony

That is a comprehensive list.

You can add

Fixed Price shift

Foreign currency exchange rate shift.

Best regards

Mike Testro

Mike Testro
User offline. Last seen 35 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Jithin

It depends on what it says in the contract.

If your recovery is for Direct Loss and Expense or Costs (JCT) (FIDIC) then it has to be the actual costs from your accounts. You can use an independant accountant / auditor to certify the costs if you do not want the Employer looking into your books.

Other contractcs require payment based on a schedule of costs - such as the daywork list (NEC).

Others base it on the rates in your Prelims BoQ. (Rare)

Best regards

Mike Testro

Jithin Kambhikanam
User offline. Last seen 8 weeks 2 days ago. Offline

Thanks Antony,

 

Ya i know that we have account for Manpower and Equipment, Insurance.

 

Engineering or Site Running Cost  - Like you had planned water , printer etc for 12 Months (Project Duration) - but now extended to 15 months so cant we claim for site running cost for 3 months.

 

Overhead Cost - We have given the contract value which had a HO overhead cost - who would be working for overall company including projects but partially - So when we bid we do include a % of the overhead cost. So cant we include a Overhead Cost.

 

Regards

Jithin

Anthony Lowery
User offline. Last seen 42 weeks 2 days ago. Offline
Joined: 24 Jan 2014
Posts: 21

Delay would cause and include daily costs of:

  1. Project Manager costs addressing the issue and trying to get the work restarted as soon as possible.
  2. Superintendent
  3. Foreman
  4. Carpenters
  5. Laborers
  6. Other employees
  7. Machinery and other rentals
  8. Storage containers
  9. Dumpsters
  10. Telephone service
  11. Temporary Power
  12. Portable toilet
  13. Builder's Risk Insurance
  14. Other insurances as required within project specifications
  15. Accounting overhead due to manpower
  16. Planning and Scheduling additional costs due to changes
  17. Additional estimator costs due to added, deleted/changed work
  18. Additional costs if the building permit lapses and work not complete due to changes.
  19. Additional building permit costs if more attributable "permit cost calculation items" are added.

All documented well as proof to alleviate grievances claimed against performance bonding

Jithin Kambhikanam
User offline. Last seen 8 weeks 2 days ago. Offline

Thanks again Mike.

But would the Client be ready to say OK to the Acoount System for "Loss and Expence" as we (Contractor) would be maintaining the account system.

Shouldnt we fix unit rate of equipment and manpower with the contract itself. Issue time sheet of everyday of the EOT to prove that we had this many people and equipment working during the EOT period so as to prove the cost aquired during the EOT period.

Regards

Jithin

Mike Testro
User offline. Last seen 35 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Jithin

That is much clearer.

If the client has caused a delay of - say - 50 days during the progress of the works and that delay extednded the completion date by 20 days the the usual procedure is to be paid the loss and expense for 20 days within the 50 days delay window.

The "Loss and Expense" is calculated from actual time related costs which will be extracted from the accounts system.

Best regards

Mike Testro

Jithin Kambhikanam
User offline. Last seen 8 weeks 2 days ago. Offline

Thanks Mike,

It was what document will help us decide the claim cost or EOT cost which should be already part of Contract so that the Contractor would be at ease. 

For example the unit charge / day for a Project Manager.

If the Project Manager had to stay 4 more months than the total project duration in the contract and the delay reason is Client then we can charge the cost per day of Project Manager for 4 months. If the unit rate of all the manpower & equipment is included in the contract then the Client cannot argue about the unit rate when we ask for the compensation.

So if we can list out what documents would help us during claim it would be a learning experience.

Thanks

Jithin

 

 

Mike Testro
User offline. Last seen 35 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Jithin

Sorry but I do not understand your question.

Best regards

Mike Testro