I have some problem regarding the EOT; I hope somebody shall help me to overcome on this situation.
The Contractor submitted his EOT Claim; alleged delays are seven but the additional work instructed by the Engineer after original completion of project is prominent delay; as stated by the Contractor.
The situation as fellow
1- Project Duration is 9 months (1-Jan-2013 to 30-Sep-2013).
2- Employer's delay occurred in month of May-2013 and due to the event; the impacted project completion date is 20-Dec-2013.
3-Contractor's delay occurred in the Month of Jul-2013 and impacted project completion date due to this event is 24-Feb-2014.
4- Engineer issued instruction for additional work at 15-Jan-2014 and it will take 2 months in engineer's opinion (not agreed at beginning of work) but work finished at 20-Apr-2014.
My question is.
A) How many days/months EOT should be entitled to the Contractor?
B) What will be compensable and non-compensable delay?
C) What will be entitlement for additional as instruction issued after project regional completion date.
D) LDs can be imposed on the Contractor or otherwise?