I am also been working on the EOT for my project. As i know the during the first interim submission of the EOT to Owner we mention the longest path.
In second submission we suggest them mitigation measures which can be taken care for the acceleration of the schedule.
The mitigation plan is always subject to the acceleration cost involved and needs an approval from the owner. If you finish the project before the EOT target that means you are entitled for the claim of acceleration cost.
Hi Bryce - sorry for th original misunderstanding.
This is why contract administartors are reluctant to award an EoT until they know the actual completion date.
Some contracts allow the CA to adjust the final award of EoT at the end of the contract but others will not allow a reduction of EoT once awarded unless there is a subsequent claim or ommission of work.
In any case since the Contractor has finished early he will only get costs to the actual completion date and/or relief of LAD's likewise.
I recall a case where a UK contractor on a road contract (ICE5) was awarded a three month EoT over the winter period.
He closed down the site for three months and returned in the spring to finish on time.
Ah, perhaps I didn't make myself clear enough.
I am trying to find cases where say the awarded EOT would indicate completion by say August, but in fact PC was achieved by say June.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Bryce,
I am also been working on the EOT for my project. As i know the during the first interim submission of the EOT to Owner we mention the longest path.
In second submission we suggest them mitigation measures which can be taken care for the acceleration of the schedule.
The mitigation plan is always subject to the acceleration cost involved and needs an approval from the owner. If you finish the project before the EOT target that means you are entitled for the claim of acceleration cost.
Hope this will resolve your quarry.
Regards,
Girish
Hi Bryce - sorry for th original misunderstanding.
This is why contract administartors are reluctant to award an EoT until they know the actual completion date.
Some contracts allow the CA to adjust the final award of EoT at the end of the contract but others will not allow a reduction of EoT once awarded unless there is a subsequent claim or ommission of work.
In any case since the Contractor has finished early he will only get costs to the actual completion date and/or relief of LAD's likewise.
I recall a case where a UK contractor on a road contract (ICE5) was awarded a three month EoT over the winter period.
He closed down the site for three months and returned in the spring to finish on time.
Best regards
Mike Testro
Ah, perhaps I didn't make myself clear enough.
I am trying to find cases where say the awarded EOT would indicate completion by say August, but in fact PC was achieved by say June.
Hi Bryce
This is normal - it is not often that an EoT is awarded during the construction period.
I am currently working on an EoT adjudication where the contract was completed 2006.
Best regards
Mike Testro