Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Delays in Practical Completion

15 replies [Last post]
Danya Pearce
User offline. Last seen 3 years 38 weeks ago. Offline
Hi All,

I am considering doing a dissertation on issues with practical completion and subsequent penalties due to this. I am just checking with you highly experienced people as to your opinions. I am currently in South Africa (and we do have issues with this). I would like an idea if this still affects other countries (with differing legal and contactual systems).

Thanks for your input

Moi

Replies

Danya Pearce
User offline. Last seen 3 years 38 weeks ago. Offline
Thanks but I dont think that will be easy to track down...... anyways, turns out my professor prefers my other topic :-( so it looks like i will be looking at business cycles and local contractors’ ability to weather the ups and downs............
Samer Zawaydeh
User offline. Last seen 5 years 39 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Danya,

If you have a soft copy that can be downloaded from somewhere, please provide the link and we will read the Form of Contract and report to you with our findings regarding your question.

With kind regards,

Samer
Danya Pearce
User offline. Last seen 3 years 38 weeks ago. Offline
Its a local South African form (JBCC)............
Samer Zawaydeh
User offline. Last seen 5 years 39 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Danya,

What Form of Contract are you working with?

And what is the Dispute does the Developer have with the Contractor?

With kind regards,

Samer
Danya Pearce
User offline. Last seen 3 years 38 weeks ago. Offline
Rafael,

thanks for that. It is unavoidable going to court. The thing is the developer is in severe financial stress now (having a developement and no buyers). My bosses are happy but i say its not a good thing as he could go bust without us getting compensated for over 6 months worth of work..... it really is a lose lose situation with the lawyers winning at the end of the day
Rafael Davila
User offline. Last seen 2 weeks 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241
Danya:

Don’t let the size of the Punch List impress you. My very first job as a field engineer had a 600 pages punch list. It was a 304 units Condo, 16 units per floor 19 floors and common facilities on ground floor, a subsidized housing for low income households, at this time was about $19,000,000US dollars, this was 30 years ago. The Punch List was an average of 2 pages per apartment unit with punch list items as; a paint stain, a scratch on a bathtub, a warped door, a missing window operator and so on.

What matters for substantial completion is if it can be used for its intended purpose. It does not mean it has to be purely 100% flawless. The owner cannot use 100% flawless excuse to reject final completion; otherwise it would be endless or at his own will.

As the Contractor, on my Claim I would start with assigning a monetary value to the final punch list pending items, with an estimate for a time to do the repairs, a simple spreadsheet should do it. For my condo although we got the final acceptance let assume some numbers:

The remaining items from the Final Punch List after review could be estimated for labor cost as per a 6 men crew, two days per floor (say 3 crews working at the same time in different floors) would be $10,000.00 at pay rates according to the year plus say the same amount for materials for a total of $20,000.00.

Grand total would be 14 days at $3,000/day liquidated damages for this job $42,000 plus $20,000 for repairs for a total of $62,000 or 3 tenths of a percent of total contract amount. Nothing to get you in red and very far from getting you broke.

Do you believe this would justify anything over $100,000 in penalty fees?

Remember these minor items not cleared out during punch list can always be cleared during the warranty period which by law in my jurisdiction is 1 year for visible defects and 10 years for hidden defects. The law protects the Owner; there is no excuse to be abusive.

As soon as the Contractor realized he was in a trap he should have asked for a monetary settlement on the pending items and request for a stoppage of the clock, this for the record.

Now is too late to avoid getting into court, is time to get some numbers for cost and time issues. Your team got to help your lawyers. Be reasonable and keep it simple as to make it easier for the judge to side with your position and write his award statement.

Best regards,
Rafael

I am using the comma as the thousands separator, per US standards.
Danya Pearce
User offline. Last seen 3 years 38 weeks ago. Offline
thanks :-)

funnily enough on this project they did terminate (but way too late) and they are going to court. big bucks involved
Mike Testro
User offline. Last seen 1 day 12 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Danya

Since you have an adjudication system then go for it.

The same risk applies in that he may go bust.

Best regards

Mike Testro
Danya Pearce
User offline. Last seen 3 years 38 weeks ago. Offline
Mike, we do have adjudication in South Africa
Mike Testro
User offline. Last seen 1 day 12 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Danya

Since you do not have adjudication in South Africa then your most direct route would be to terminate the contract and pursue him through the courts - the risk is that he will go bust before you get your money.

Best regards

Mike Testro
Danya Pearce
User offline. Last seen 3 years 38 weeks ago. Offline
Thanks Mike,

I think this is worthwhile to explore and find out what is going on in my local industry.

We had this HUGE property boom from the early millenium and it ground to a halt recently (based on the global issues). Many large scale projects have stopped (like Dubai) midway through construction with developers going bust OR in a project I was in, the client (a real shark) is imposing these penalities due to the fact that he cant sell his apartments and is looking to make money from the contractor. I do think we, as the contractor had many issues, but the contractual definitions of completion has left this project open to major risks.......
Mike Testro
User offline. Last seen 1 day 12 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Danya

It is rare for there to be a contractual definition of what conditions are required for practical completion.

Generaalt speaking if the building is fit for occupation - subject to a few punch items - then it is practically complete.

This will include final test and commissioning - operations and manuals and training.

If the occupier is eager to take possession then this is normally not a problem but if there is no eager occupier then the owner is naturally reluctant to release the contractor from his obligations.

I an currently engaged in an adjudication on this very point.

Best regards

Mike Testro
Danya Pearce
User offline. Last seen 3 years 38 weeks ago. Offline
Thanks for your responses.

I have noticed in many building projects, a certain ’vagueness’ in the definition of what defines practical completion. This has caused many issues towards the end of the project whereby the architects and engineers issue huge completion lists and if the contractor fails to complete them, penalties are applied. I havent as yet seen a definition in the actual contract defining this and perhaps this is the avenue to pursue?

I will look at the links posted and comment. thanks for that :-)
Samer Zawaydeh
User offline. Last seen 5 years 39 weeks ago. Offline
Joined: 3 Aug 2008
Posts: 1664
Dear Danya,

You need to research the type of Contracts that are adopted in your part of the world and review the Conditions of Contract.

Usually the verification of the "Practical Completion" has an independent clause and the "Delay" has a clause of itself.

Delay in Practical Completion should be studied and the party causing this delay will be identified subsequently. If the Owner is the cause of the delay, then the Contactor might claim for overheads. On the other hand, if the Contractor is the cause of delay, the Client might implement delay penalties.

If you ask more specific questions, we will be able to provide you with detailed answers hopefully.

Good luck in your dissertation,

Samer
Rafael Davila
User offline. Last seen 2 weeks 3 days ago. Offline
Joined: 1 Mar 2004
Posts: 5241
Danya

If by practical completion you refer to what we know as “substantial completion” then this date stops the clock for the purpose of penalties / “liquidated damages” determination.

After this date the contract usually provides specific time duration for the Contractor to clear Punch List items, if not then the Owner can deduct from the final payment a reasonable amount. The Substantial Completion Date plus this additional time limits the Final Completion Date unless both parties agree to continue either by means of a Change Order or by means of their actions.

In my jurisdiction “means of their actions” applies only to private contracts as for public job contracts the agency cannot make payment for works performed out of the contract time. Therefore EoT are serious issues at the end of public works.

http://www.bergersingerman.com/newsletter/NewsletterPDF/WertmanOct08.pdf " target="_blank" > The Doctrine of “Substantial Completion “on Construction Projects
ftp://imgs.ebuild.com/woc/C730162.pdf " target="_blank" >What is substantial completion
PROCEDURES RELATING TO PRACTICAL COMPLETION

Best regards,
Rafael