Hi all,
If the Contract states that the float from planned completion to contractual completion of the different sectional milestones and the final completion date belongs to the Contractor, would you then make activities for that float in the baseline programme or just leave as is and take up the discussion at a later stage should it become relevant?
If including activities for the terminal float and link up from planned completion to contractual completion it would mean many activities would suddenly become critical, though some activity paths would in most projects still have float up to the planned completion.
If not including activities for terminal float it would not be possible to easily ascertain between the terminal float value and the actual total float for each activity.
The "declaration" of terminal float or not in the programme would most probably have a huge impact when discussing claims at a later stage.
Best regards,
Bo
Replies