Hello all you propeller heads...
Can anyone tell me where the term ’Terminal Float’ came from? I have heard it referred to recently in conjunction with the NEC contracts. A Google search on those terms does throw up a few learned papers that mention it and there are a couple of references to it in other threads on PlanningPlanet.
The mother of all glossaries, the Wideman Comparative Glossary of Project Management Terms v3.1 (
http://www.maxwideman.com/pmglossary/index.htm) does not mention it.
I can’t find reference in the NEC suite (but then it is a massive document). I realise it is jargon connected with ’time risk allowances’ (clause 31.2).
I imagine it was contrived by a non-planner and really means time contingency (or buffer) at the end of the project.
My view, for what it’s worth is, simplistically, that float is unallocated time within a programme, contingency is allocated time (say, to take account of unexpected events) so, therefore, float is not contingency and mixing the terms will lead to confusion.
For instance: A contractor provides a contingency period at the end of the project - lets say he describes it as such and it occupies the one month period between the planned end of his works and the contractual completion date. Now, if the employer omits some work that take makes the planned programme is one month shorter, in most contracts the employer cannot reduce the contract period. In my view (which is still under development) the contingency period stays at one month and there is now also an additional free float period of one month at the end of the programme. I believe that free float period now belongs to the programme in the usual fashion to be used on first come first served basis but the contingency period can only be used by the contractor (and he only has to do that once the free float is used up).
Apologies for rambling.
Regards
David
Replies