Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Arbitration rules as per International Chamber of Comm

7 replies [Last post]
Sreejish Vishnu
User offline. Last seen 11 years 36 weeks ago. Offline
Joined: 11 Nov 2005
Posts: 32
Groups: GPC Qatar
Hi Experts,

If the disputes are to be finally settled by the rules of Arbitration of International Chamber of Commerce, is it required to follow any particular method for delay analysis.

Like in US and UK courts the As Planned Impacted method would not have a legal stand, how is it as per ICC rules. Have they set aside anything for delay analysis.

Replies

Roland Tannous
User offline. Last seen 12 years 46 weeks ago. Offline
Joined: 15 Oct 2009
Posts: 84
Groups: None
Allow me to add that the analysis method is per project basis depending on the situation and the context of the whole project and how things were handled, how much information is available,etc..

I agree with someone who stated earlier that the arbitration model of the ICC doesn’t specify a particular analysis method. Actually it doesn’t really touch on this subject as far as i remember in any of its articles
Regards
Mike Testro
User offline. Last seen 36 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Sreejish

The claim will be rejected if the method used is not the correct one to use in the circumstances.

In a recent case - Great Eatsern v Laing - the experts each used a different method and the one using As Built but For was thrown out while the Impacted as Planned won.

Time Impact Analysis is usually acknowledged as being the most realistic but I would not use it for a sub-contract package where an As Built v As Planned would be better.

The first skill of a delay analyst is to know which method - or combination of methods - to adopt.

I renently put together a delay and acceleration claim by adjusting the calendars - no known method at all.

Best regards

Mike Testro
Sreejish Vishnu
User offline. Last seen 11 years 36 weeks ago. Offline
Joined: 11 Nov 2005
Posts: 32
Groups: GPC Qatar
Thanks Andrew it really helps to know that the claim is not going to be rejected just for the method used.

Mike - as always thanks for your expert comments.

Ravi - those links were too good, you bloody became a master of information sources.
Andrew Tweeddale
User offline. Last seen 13 years 21 weeks ago. Offline
Joined: 8 Oct 2009
Posts: 6
Groups: None
Hi Shreeji

The ICC Arbitration Rules do not specify any particular form of delay analysis. It is for the claimant to present his case as he considers appropriate and I have not yet come across an ICC tribunal which has specified a particular form of delay analysis to be used.

I have seen an impacted as-planned used in an ICC arbitration where the claimant argued that this was the best form of delay analysis because in the curcumstances. I have also come across as-planned vs as-builts being used in ICC arbitrations. What seems to be clear, however, is irrespective of the type of programme you use, if it is not based on facts then it is likely to be rejected by the tribunal.

Hope this helps

Andrew
A D
User offline. Last seen 4 years 2 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Shreeji,

Check this site also. Here u can find lot of case-studies.

http://www.bailii.org/

Cheers,

Ravi
Mike Testro
User offline. Last seen 36 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4418
Hi Shreeji

If it has got as far as an International Arbitration the two sides will each have appointed Experts in the various heads of dispute.

The delay amaysis experts will be required by the Arbitrator to agree on the software and the method of analysis.

If they do not agree then the arbitrator will tell the experts which is his preference - which it would be wise to follow.

Remember that the role of the expert in any tribunal is to assist the Arbitrtor / Adjudicator / Judge from a neutral position - any hint of favouratism will result in the case being dismissed.

Best regards

Mike Testro
A D
User offline. Last seen 4 years 2 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Hi Shreeji,

Check the link below:

http://www.aacei.org/technical/rps/29R-03.pdf

Refer to page no. 11

May be of some help