Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

When is the commencement date

5 replies [Last post]
carlo antinio galang
User offline. Last seen 16 years 5 weeks ago. Offline
Joined: 2 Feb 2007
Posts: 6
When is the first date of construction of a project? is it on the notice to proceed or the date when the contractor receive its downpayment?

Replies

carlo antinio galang
User offline. Last seen 16 years 5 weeks ago. Offline
Joined: 2 Feb 2007
Posts: 6
k guys thanks for your replies
Omer Hassan
User offline. Last seen 16 years 3 weeks ago. Offline
Joined: 6 Jul 2008
Posts: 18
Groups: None
As per FIDIC clause 41.1

The Contractor shall commence the Works as soon as is reasonably possible after the receipt by him of notice to this effect from the Engineer, which notice shall be issued within the time stated in the Appendix to Tender after the date of the Letter of Acceptance. Thereafter, the Contractor shall proceeded with the Works with due expedition and without delay.

In Appendex to Tender Employer can mention the time for commencement as per following example:_

Time for Commencement 41.1 Within 14 days from the date of receipt of Engineer’s Notice to Commence which shall be issued within fourteen (14) days after signing of Contract Agreement.

Regards,
Omer
A D
User offline. Last seen 3 years 46 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Do u hav any tender program??

Does it say anything, anything abt it?

If contract is based on FIDIC 1999, then Check Clause 8.1 (b), which says "Contractor shall commence the work (incld., mobilisation and procuremnet) promptly after the Commencement Date and shall proceed with the Works with due expedition and without delay IN ACCORDANCE WITH THE TENDER PROGRAMME and upon certification by the Employers Representative, the programme submitted under Sub-Clause 8.3"

Cheers,

Ravi
Anoon Iimos
User offline. Last seen 2 years 37 weeks ago. Offline
Joined: 22 Sep 2006
Posts: 1422
"when is the first date of construction of a project?" it is the day you started your layout and digging your foundation, other dates, you will only find on paper (but don’t lose the paper, you might not get paid)
Andrew Flowerdew
User offline. Last seen 2 years 46 weeks ago. Offline
Joined: 14 Dec 2004
Posts: 960
Groups: None
Carlo,

A definition will be (or should be) written in the contract documents somewhere.