Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Show Completed Task as Critical

6 replies [Last post]
Daniel Stoker
User offline. Last seen 5 years 17 weeks ago. Offline
Joined: 8 Jun 2017
Posts: 8
Groups: None

Hello,

I'm looking to analyse the critical path of a part-completed programme for a project, however, tasks that are 100% complete or have been progressed do not show up as critical.

Is there any way of showing progressed items as critical without having to remove the existing progress from each task?

Regards

Dan Stoker

Replies

Daniel Stoker
User offline. Last seen 5 years 17 weeks ago. Offline
Joined: 8 Jun 2017
Posts: 8
Groups: None

Thanks Trevor,

The contradictory critical path of the as built is essentially what I was looking for.

Regards

Dan

Daniel Stoker
User offline. Last seen 5 years 17 weeks ago. Offline
Joined: 8 Jun 2017
Posts: 8
Groups: None

Thank you Abbas,

That is a good way to visually demonstrate.

Regards

Dan

Trevor Rabey
User offline. Last seen 2 years 24 weeks ago. Offline
Joined: 29 Nov 2005
Posts: 530
Groups: None

Daniel, the answer is "no" and the reason is the definition of "critical". The entire concept of the critical path method is only applicable to tasks which are planned/scheduled in the future. Once a task has an actual start date and an actual finish date, which of course must be in the past, then it's earliest and latest start and finish dates no longer exist, or rather, they must be the same as actual start date and actual finish date. I suspect that you are trying to find something called an "as built critical path", which is just a contradiction in terms. Any help?

Abbas Shakourifar
User offline. Last seen 2 years 36 weeks ago. Offline
Joined: 11 Jul 2006
Posts: 15

Hi Daniel,

An actual activity cannot be critical by definition. However, there are different ways to "Show" something critical.

If by showing you mean color "Red" follow these steps:

- Make a user-defined code and select the activities which you like to show as critical.

- On the Bar format table, Find the "Actual" Bar format, change your filter and make sure the coded activities are not included.

- on the Bar format table, add a new one, use your code to filter the activities which you need to shown as critical and format them as"Red".

I hope it helps.

Abbas

Daniel Stoker
User offline. Last seen 5 years 17 weeks ago. Offline
Joined: 8 Jun 2017
Posts: 8
Groups: None

Thanks Mike,

I had thought as much.

Regards

Dan Stoker

Mike Testro
User offline. Last seen 23 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Daniel

No

Best regards

Mike Testro