Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Formula in Asta - Slip

1 reply [Last post]
Paul Woodley
User offline. Last seen 1 year 12 weeks ago. Offline
Joined: 2 Nov 2016
Posts: 9
Groups: None

Column to show "0"

-If the task is in the past AND 100% complete
-If the task is in the future and 0% complete

Columns to show result from the following formula;
(DateDiff(Start, Today)-[~LP].ActualDuration)
IF
It is in progress and being progressed.


If the task is in the past with 0% progress it should be showing a value. The difference between today and the start of the task (latest progress)

 


I hope that gives an indication and enough detail as to the requirements.

I am in a bit of a pickle. Hoping someone could shove me in the right direction. I need the following (regarding slip) Column value to show "0" IF; - The task is in the past AND 100% complete- The task is in the future and 0% complete Column value  to show result from the following formula (the bit I could get to work);DateDiff(Start,Today)-[~LP].ActualDurationIF- The task is in progress  IF the task is in the past with 0% progress it should be showing a value - the difference between today and the start of the task (latest progress)   I hope that gives the detail explicitly enough and hope someone can help out! I am tearing my hair out over this....

Replies

Mike Testro
User offline. Last seen 23 weeks 2 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Paul

Why go to such bother.

Set your reschedule window to block out completed tasks.

Or show the Percent complete Nr 0% to 100% and that will show the data you want. 

Best regards

Mike Testro.