Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to assign resources to part of a tasks

4 replies [Last post]
Chris Wilson
User offline. Last seen 1 year 29 weeks ago. Offline
Joined: 21 Oct 2016
Posts: 22
Groups: None

Hi,

Does anyone know how to assign a resource for a period in the middle of a task?

I have a number of tasks that are say 10 weeks long, however I would like to assign different resources to the first 4 weeks the middle 2 weeks and the last 6 weeks but cant work out how this can be achieved. I assign the resources as non modelled as I do not want them effecting the duration of the task.

Any help would be appreciated.

Replies

Ben Taunt
User offline. Last seen 1 year 4 weeks ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

Hi Chris,

Mike and Paul give good advice on why not to do this, and on other ways of acheiving the same.  But for reference, you can have a resource allocation in Powerproject of a different duration to the task.  It can be as simple as modifying the length of the resource allocation bar as if it was a task (click on the end of the bar and drag left or right).

Powerproject does however also have a full non-linear resource allocation feature, which is the last tab of information on the resource allocation properties menu (right-click on the resource allocation bar).  See the help file for more details.

Oh - and check out the resource usage view, for an editable grid-like window under the bar chart showing where resources are working!

Ben @ Powerproject

Paul Harris
User offline. Last seen 1 year 40 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618

Multiple Tasks on one line will do this.

Regards

Paul E Harris
BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner
Managing Director and President
Eastwood Harris Pty Ltd, Australia
http://www.eh.com.auhttp://www.primavera.com.au and http://eastwoodharris.com.
Project Control Consultants and Planning and scheduling software book and training material publishers

Paul Harris
User offline. Last seen 1 year 40 weeks ago. Offline
Joined: 11 Apr 2001
Posts: 618

Multiple Tasks on one line will do this.Regards

Paul E Harris
BSc Hons, Certified Cost Engineer, PRINCE2 Practitioner
Managing Director and President
Eastwood Harris Pty Ltd, Australia
http://www.eh.com.auhttp://www.primavera.com.au and http://eastwoodharris.com.
Project Control Consultants and Planning and scheduling software book and training material publishers

Mike Testro
User offline. Last seen 4 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Chris

You can split the tasks into sections using the Split Task option.

Then you can add resources to each section

Make sure that they are logic linked.

Better stiil set up different tasks for each section - 10 weeks is too long - 10 days is more realistic.

Best regards

Mike Testro