I was born and raised with Primavera but recenlty started using Asta as well to broden my knowledgebase. The addaptaion has not been smoth and i struggle with the idea that Asta is somehow superior to P6. But maybe it's just my way of thinking that is at fault?
Here is an example i struggled with all day today.
Activity 15 is not started. 0% complete. Has both succesors and predeccesors. Yet somehow when i scheduled the project not only did it jump backwards so that it starts before it's predecessors are completed but it also starts (and ends) before the status update line / Datadate?
How on earth can this be so?
And in addition activity 4 has been marked as finished and i've set the actual date to be 2017-09-22.. yet when i schedule it jumps to actual start 2017-08-31! Eventhough its predecessors are completed at 2017-09-22.
To me this goes against all logic and reason. So either the program is faulty or there is something that i haven't taken into account. Which is it?
Replies