Column drop down list for codes

3 replies [Last post]
Farhad Khondaker
User offline. Last seen 4 years 24 weeks ago. Offline
Joined: 30 Sep 2014
Posts: 11
Groups: GPC Malaysia
    Hi All This is my first post! I am fairly new to ASTA and have come across a few interesting things that P6 doesn't have! When adding a coded column, how would i add a drop down list to the fields? Rather than having to drag from the code library from the left hand side to the Gants chart bars. Hope the above query is clear. Thank you for your help in advance guys!

Replies

Farhad Khondaker
User offline. Last seen 4 years 24 weeks ago. Offline
Joined: 30 Sep 2014
Posts: 11
Groups: GPC Malaysia

Thank you Mike and Ben.

 

Farhad

Ben Taunt
User offline. Last seen 1 year 23 weeks ago. Offline
Joined: 16 Jan 2012
Posts: 113
Groups: None

Hi Farhad,

When you have a column in your spreadsheet showing the code library assignments, these cells should become drop-down lists when you click in that cell - which is an alternative to having to drag on your codes.

If you amend the properties of the code library by simply right-clicking on the code library within the list on the far left (project view), you can make the code a 'single select' which means that only one code from each category can be assigned.  Perfect for items which can only be one option (e.g.. build stage?), as opposed to categories when it might be appropriate to have multiple codes (e.g.. Trade Contractors?).

Thanks,

Ben @ Asta Powerproject

Mike Testro
User offline. Last seen 23 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Farhad - Welcome to Asta and welcome to PP.

The columns and the bar chart are usually linked - type something in the right column and it appears on the chart.

I think the drag and drop feature is one of the best in PowerProject - particularly when used in conjunction with a filter.

You can have as many codes as you like but it only shows one on the chart.

Best regards

Mike Testro