Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Baseline Vs Actual Progress in Line of Balance

2 replies [Last post]
Lo Gary
User offline. Last seen 9 weeks 6 days ago. Offline
Joined: 6 Feb 2010
Posts: 52
Groups: None

Dear,

 

Could we show both baseline and Actual Progress in the same Line of Balance, so that we could compare whether the progress is ahead or delay in Line of Balance?

 

 

Regards,

 

Gary Lo

Senior Project Mnager

Replies

Lo Gary
User offline. Last seen 9 weeks 6 days ago. Offline
Joined: 6 Feb 2010
Posts: 52
Groups: None

Dear,

 

The problem is whether this could be shown in Line of Balance rather than in Gannt Chart.

Of course, this could be done in Gannt Chart.

 

Thank!

 

Regards,

 

Gary Lo

Vipin lal
User offline. Last seen 8 years 25 weeks ago. Offline
Joined: 21 Aug 2014
Posts: 2
Groups: None

Hai Gary,

hope the question is how to show the base line and actual progress(ahead/delay) in the same time

for that you have to

1.Maintain the base line of the program 

Project Menu>maintain Baseline>add>Save a copy of the current project

2.Assign Baseline

Project Menu>Project Baseline>''select your program''  and Primary Baseline>''select your program''

 

   Dont forget to tick the primary Baseline display options in the Bars in gantt chart

 

Thanks

VL