Can't get rid of Line of Balance when trying to print

2 replies [Last post]
Yasine Ali
User offline. Last seen 5 years 12 weeks ago. Offline
Joined: 12 Aug 2015
Posts: 18
Groups: None

Hello everyone, newbie in planning here.

I am trying to print off a project.

However when I try to print the Line of Balance view is still visible even though I pressed the "hide" button in format.

Does anyone have any suggestions of how I can get rid of this when printing?

Thanks in advance!

Replies

Mike Testro
User offline. Last seen 11 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Yasine - Welcome to planning planet.

Good that you sorted your problem.

Next time please only hit the SAVE button once.

Best regards

Mike Testro - Moderator.

Yasine Ali
User offline. Last seen 5 years 12 weeks ago. Offline
Joined: 12 Aug 2015
Posts: 18
Groups: None

Okay so I managed to find it.

If you click on View and then press More Graphs there is an option to delete the line of balance.