Finish start links

S
Sarah Smith 👤 Member for 12 years 1 month

I am new to planning and am trying to understand link logic and am getting very confused. I have only used finish to start links or finish to finish. Can you please tell me why have a start to finish and what does it do different to a finish to start. It seems to be the same thing to me. One task ends before another can start.

M
Mike Testro 👤 Member for 20 years 7 months

Hi Sarah

Using Finish Start links is the correct procedure for the construction industry so please continue with that method.

Other schedulers use Start Start links with a lead lag but this is a lazy approach - I have had many a debate in PP on this topic so maybe another will start up.

There is no place for a Finish Finish link unless you have to close out a SS link creating a "ladder" sequence.

A ladder is fine for a manufacturing but not much use in construction.

There is no point in Start Finish link in any programme although I have seen it used once when a construction director was using them to create an As Late As Possible sequence. When I showed him the ALAP button he changed his ways.

The only place for a FS Lead Lag is to allow for drying out or curing when the time lag must be in calendar days.

Best regards

Mike Testro

Featured Partner

Top Posters

mxsiegel
0 posts
Mattvtek
0 posts
Gareth Evans
3 posts
PP Admin
3, 129 posts
Rajkamal Tangirala
5 posts
Rahul Kumar
1 posts
blake333_
0 posts
Jeamiell Ostrovsky
2 posts
Hamzah Ahmed
0 posts
Quinton van Eeden
3 posts