Change start time and finish time (hours and minutes)

2 replies [Last post]
Farhad Khondaker
User offline. Last seen 3 years 34 weeks ago. Offline
Joined: 30 Sep 2014
Posts: 11
Groups: GPC Malaysia

Hi All.

My query to end this week is the most difficult to resolve. I have  figured out the issue but failed to fix it.

My program is based on weeks and days, however when viewing the time (hours and minutes) format. My project start and finish links are inconsistent with time. I realised this when my durations didn't add up.

For eg. Ideally a 3 day duration- Start Monday, finish Wed evening. However my programme, 3 day duration. starts Monday, finishes midday Thursday.

The activities start and finish times are inconsistent i.e. start 0830, 10:00, 11:00 and finish 16:00, 17:30, 0830 (the following day).

The reason as to why it does this is it is a p6 export, that came with the dodgy times. When creating new programs the times are fine. However when copying and pasting chunks from the p6 export in to a new asta program the issue arises again.

 

Unfortunately, i can not redo the progrram as its 1800 activities long.

Is there an easy way to globally change the start and finish times, and locking the durations in place?

 

Thank you for your help.

 

Replies

Farhad Khondaker
User offline. Last seen 3 years 34 weeks ago. Offline
Joined: 30 Sep 2014
Posts: 11
Groups: GPC Malaysia

Hey Charlotte,

 

Thank you for the information- was helpful.

Regards,

Farhad

Charlotte Underhill
User offline. Last seen 6 years 12 weeks ago. Offline
Joined: 4 Jul 2016
Posts: 15

Hi Farhad,

The reason the software will be doing this is because of the work pattern assigned to the calendar, try highlighting all your tasks (ctrl A) and then dragging another calendar onto one of your tasks in the gant chart, this will keep the durations the same as long as the total working hours in a day are the same.

I hope this helps.

Regards,

Charlotte