Re-Schedule

I have been given a programme to review. It Asta V12. When I re-schedule, I find 2 tasks that have

  1. No Links (in or out)
  2. No constraints of any kind

After I re-schedule (F9), the tasks “just sit there”. They do not move back to the re-schedule date. I can “move” them to another date, and again they just sit there. What is causing this??

Ronan

M
Mike Testro 👤 Member for 20 years 6 months

Hi Ronan

Goto Tools > Options > Reschedule and you will see three options for tasks with no links.

Yours is pobably set to > "Leave as drawn within constraints"

Choose any of the other two to get a different option - the task will probaly fall back to day 1.

Best option is to put some logic onto it.

Best regards

Mike Testro

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts