Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Re-schedule

4 replies [Last post]
Ronan Niland
User offline. Last seen 7 years 17 weeks ago. Offline
Joined: 21 Jun 2012
Posts: 10
Groups: None

After I press F9 to re-schedule a box appears on the screen, asking what date to straighten the progress line to. I turned that box off, and now I want to turn it on again. How do I do this ??

 

Thanks 

 

Ronan

Replies

Ronan Niland
User offline. Last seen 7 years 17 weeks ago. Offline
Joined: 21 Jun 2012
Posts: 10
Groups: None

V 11

Yasin Vural
User offline. Last seen 9 years 2 weeks ago. Offline
Joined: 7 Jul 2012
Posts: 5
Groups: None

Ronan Niland, are you using v11 or v12? 

Chris Rymer
User offline. Last seen 3 years 8 weeks ago. Offline
Joined: 11 Jun 2010
Posts: 32
Groups: None

Ronan

To turn the dialogue box back on (in Version 12) go to File - Options - General. On the right hand side is a button called Do not show again prompts.... Click on this and select the Reset button. This will will restore the box you are after.

Regards

Chris Rymer

 

Mike Testro
User offline. Last seen 35 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Ronan

There are two sets of adjustments - assuming you are using the Icons and not that horible ribbon.

1. Tools > Options > Reschedule to set the progres line reschedule date.

2. Format > Barchart > Progress to turn the line display on or off plus other toggles.

Best regards

Mike Testro