Planned Start

2 replies [Last post]
Hemant Bharat
User offline. Last seen 7 years 39 weeks ago. Offline
Joined: 11 Nov 2010
Posts: 8
Groups: None

I would like to know how to switch on Planned Start and Planned finish date when baselining the projects.

Replies

Mike Testro
User offline. Last seen 13 hours 57 min ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Hemant

Welcome to Planning Planet

If you want to see the baseline bars in seperate rows with start and end dates then there is a switch in > Format > Barchart > Baselines > Show Baselines on their Own Lines.

If you just want a different set of date columns then go to Table Definition and add two more columns for Start and Finish and in the Data Drop Down select the Baseline that you want.

You can also set a column to show the diference in days.

Hope that helps

Best regards

Mike Testro

Hemant Bharat
User offline. Last seen 7 years 39 weeks ago. Offline
Joined: 11 Nov 2010
Posts: 8
Groups: None

What I meant was how to switch on the date columns with the "planned start" and "planned finish" dates. I have baselined the project already.