Cost Assign

1 reply [Last post]
Martin Gomez
User offline. Last seen 12 years 11 weeks ago. Offline
Joined: 29 Apr 2010
Posts: 14
Groups: None

Hello everyone 

                           I am cost loading my programme,we use sub contractors for majority of our packages.there is  a lumpsum amount for the subcontract packages. do i assign it propotionally to all the activities ?or is there another way to costing .

can anyone give me guidance as i have never cost loaded my programmes before.where can i get more information on cost loading programmes.

 

Regards S

achin Martin

Replies

Tekin Guvercin
User offline. Last seen 11 years 15 weeks ago. Offline
Joined: 30 May 2007
Posts: 20
Groups: TILOS

354
costasta.jpg
Its really depends how you detailed your schedule. With ASTA you can assign cost to each activity or Sumarry activity. It will distribute with weithed factor. The biggest advantages of ASTA you can assign cost to activities without creating Resource. If you have your subcontractor you can create cost under library and model it in three types. (TIME BASE COST, FIX COST or UNIT COST).

Go to library   create to costs and assign it.

 

I attached here picture with both example. Design A is cost assing to Summary Level (like WBS), Second is detail to activity. Both way possible. if you not solve your problem, contact with me I will send you some detail documents.