Automatically assign codes

2 replies [Last post]
Konstantinos Pars...
User offline. Last seen 1 year 45 weeks ago. Offline
Joined: 8 Mar 2006
Posts: 21
I am trying to find out whether there is a way to set up an automated assignment of codes once it is partly or 100% progressed, i.e. once I input the progress of the task, the code will automatically change to (e.g.) "Partly Completed" or "Completed" (which I have set up!). I am using PowerProject V9.

Thanks!

Replies

Andreas Ronczka
User offline. Last seen 13 years 50 weeks ago. Offline
Joined: 3 Jul 2006
Posts: 15
Groups: None
You could also use a column with the token "priority" in the spreadsheet and set in the field "indirection" the formula "Percent complete#0#99".
As result you get a colum where 0% shows RED, 1-99% shows ORANGE and 100% shows GREEN. Not a code but looks simelar.

HTH

Andi
Tom Howard
User offline. Last seen 9 years 11 weeks ago. Offline
Joined: 20 Jun 2003
Posts: 119
Groups: None
Use the progress token called "Process State"... titles cant be changed but represent similar headings to those you require.