Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Critical Links

3 replies [Last post]
Craig Adams
User offline. Last seen 13 years 34 weeks ago. Offline
Joined: 11 Oct 2006
Posts: 71

Hello Fellow Planners,

Trying to change the thickness of critical links so they are more visible - only seem to be able to change color.

Anyone know how to change thickness?

Thank you in anticipation,

Craig Adams

Replies

Mike Testro
User offline. Last seen 31 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Craig

You are right - can only change colours and names on pre set links.

One for Andrew Willard for version 11-3

Best regards

Mike Testro

Craig Adams
User offline. Last seen 13 years 34 weeks ago. Offline
Joined: 11 Oct 2006
Posts: 71

Hello Mike,

I've been in this section and can change various aspects of all links however, with the critical links I only have the option to change the colour.

Cheers,

Craig Adams

Mike Testro
User offline. Last seen 31 weeks 6 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi Craig

In the library explorer links dialogue there is a section where you can change colour - style and thickness of all links and add any number of new categories.

I use resource levelling links that can be switched on and of in the Options Reschedule dialogue.

Best regards

Mike Testro