Current view progress only calculated and not hidden

1 reply [Last post]
Bernie Kurland
User offline. Last seen 14 years 23 weeks ago. Offline
Joined: 18 Aug 2010
Posts: 2
Groups: None
Has anyone tried this
I want to calcilate current view progress and not to include any activity progress not in current view
This will apply to activities using a filter whether they have progress or not but to exclude typically "by others" for example

Bernie

Replies

Mike Testro
User offline. Last seen 13 weeks 1 day ago. Offline
Joined: 14 Dec 2005
Posts: 4420
Hi Bernie

Welcome to Planning Planet

You can enter progress on a filtered view on all or selected tasks and it will be effective when you drop the filter.

Make sure you tick the Link Around Completed Tasks when doing the excercise.

Best regards

Mike Testro