While doing some analysis of our construction program, I have drawn the following conclusion;
Im Confused…….
I have 1 activity on a 9 hr/day calendar (7:30 – 4:30), 10 days in duration. The activity starts at 0730 on the first day and finishes at 15:30 on the 9th day. This is some 1 day 1 hour early.
What I reckon is that we say we are able to work for 9 hours each day and the system default is 8 hrs per time period.
Therefore the planned 10 days * 9H/d = 90Hrs duration is calculated at 8H/d for 10 days based on a 9hr/d calendar therefore giving an early finish equal to 10 hours early. I.E 9th day at 15:30Hrs.
Now how do you reckon this will extrapolate over a 2 year construction program that is working on a construction calendar equal to 7 days/week 9 hrs/day when as far as Primavera is concerned all durations and therefore end date is calculated based on 8Hr/d, 40Hr/W, 172Hr/M, 2000Hr/Y. When what we’re saying is we need 9H/d, 63H/w, 273H/m, and 3276H/y less Easter and xmas break.
Has anybody else confirmed this??
How do I fix it??
Have I grabbed hold of the right end of the bull??
I don’t have access to the global admin settings.
Andy