Senior Planning Engineer, FSB , SUB STATION & INFRASTRUCTURE

START Date: 
March, 2006
END Date: 
March, 2012

RESPONSIBILITIES:

1. Prepare Program
Set up project calendar
Set up Activities and Coding with construction managers
Set up resource requirements using standard outputs
Sequence & link the required activities, within given milestones.
Establish the critical path through the program
Prepare information schedule in conjunction with construction manager
Prepare subcontract appointment schedule with construction manager

Senior Planning Engineer, FSB, SUB STATION & INFRASTRUCTURE

START Date: 
March, 2006

RESPONSIBILITIES:

1. Prepare Program
Set up project calendar
Set up Activities and Coding with construction managers
Set up resource requirements using standard outputs
Sequence & link the required activities, within given milestones.
Establish the critical path through the program
Prepare information schedule in conjunction with construction manager
Prepare subcontract appointment schedule with construction manager

Senior Planner, Motorola, All Development Projects for Infrastructure

START Date: 
February, 2001
END Date: 
October, 2003

Feb 2001 to Oct 2003:-
Motorola – Planner – coordinator     
IT/Telecommunications
Joined Motorola on 19th February 2001 to work in Program Management Office implementing an Enterprise Project Management System (Primavera TeamPlay/P3e) in the UK. SME (subject matter expert), System Super User, Application Administrator and approved trainer for the EPMS covering Europe, Middle East and Africa.

Experience Hours (Planning & Scheduling): 
5000
Experience Hours (Cost Management): 
2000

Freelance Senior Planner, Enterprise plc, All

START Date: 
September, 2005
END Date: 
February, 2006

Employed in IT department to review and maintain Development and Mobilization schedules for an MoD joint venture programme for national property maintenance. Also reviewed schedule and data integrity and provided recommendations on methodology improvements. Designed bespoke layouts and reports for management. Produced process for transfer of schedule data to other companies within the joint venture.

Experience Hours (Planning & Scheduling): 
1400
Experience Hours (Cost Management): 
1000

Primavera Consultant, British Energy / Morson International, All Engineering Outage and Development projects

START Date: 
February, 2006
END Date: 
October, 2008

Energy I was commissioned to re-organise the planning processes and merge two divisions into one so that they used standard process. There are over 80 planning staff located at 8 nuclear power stations, one coal fired station and three supporting business units throughout the UK.

The first task was to examine the existing processes and procedures, in addition a health check was carried out on the Primavera infrastructure, including a thorough assessment of data integrity and schedule integrity.

Experience Hours (Planning & Scheduling): 
5500
Experience Hours (Cost Management): 
1400
Experience Hours (Forensic Analysis): 
100