Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Power Plant 850MW

senior time scheduling engineer, THOST Projektmanagement GmbH for AE&E Inova and IHI Euro Power GmbH, Power Plant 850MW

START Date: 
August, 2010
END Date: 
September, 2012

Senior Project Engineer for Powerplant Erection in Germany

responsible for contractual items of boiler, flue gas cleaning, boiler house (steel, concrete), coal handling

Size of schedule: round about 6000 activitys

Planning of commissioning schedule.

Progress report to project manager, client, head of company

S-Curves for critical items

Detail Planning of boiler welding, Critical Erection Items

schedule analysis of sub contractors schedule and contracts

 

Market Place

No results found... (try selecting a different content filter)

Syndicate content