Monthly Reports

Client Side Senior Planner-Esso Thailand, Foster Wheeler Thailand, SBOU Project Exxon Mobil Thailand

START Date: 
September, 2012
END Date: 
December, 2013

Assist EPC eEstablished and develop contract schedule and baseline

Review EPC monthly reports and progress backup

Review and comments EPC project control document procedure and sugges recomedantions

Developed reporting forat for produvtivty and level 4 progress calculation sheets

Monthly analysis of EPC forecast schedule and look ahead plans

Submit customize reports to client monthly

Created and update level 2 management schedule on milstone profressional

Experience Hours (Planning & Scheduling): 
2550

Planning & Scheduling Engineer, A&P Paraskevaides &Partners , Jumeirah Beach Residence

START Date: 
May, 2005
END Date: 
November, 2005

 

·         Preparation and Execution of schedules using Special software P3 by updating day-to-day progress, weekly and monthly progress reports.

·         Resource/Progress Histograms,S-Curves, Bar charts, etc.

·         Preparation of look-ahead schedules, monthly reports, Analysis report comparing with target with base schedules, etc.

Assistant Construction Planner/Scheduler; Maintenance Planner, EIA XXI - Repsol, SKR01 SKSOL LUBE BASE OIL COMPLEX

START Date: 
September, 2012

Assigned to SKSOL, a joint venture of REPSOL S.A. (Spain) and SK Lubricants (Republic of Korea), to schedule the construction of a new lubricant plant, including two process units, an onsite tanks area and a seaside tanks area, reporting to the Organization Project Management Team

Assistant Construction Planner/Scheduler; Maintenance Planner, EIA XXI - Repsol, SKR01 SKSOL LUBE BASE OIL COMPLEX

START Date: 
September, 2012

Assigned to SKSOL, a joint venture of REPSOL S.A. (Spain) and SK Lubricants (Republic of Korea), to schedule the construction of a new lubricant plant, including two process units, an onsite tanks area and a seaside tanks area, reporting to the Organization Project Management Team

Assistant Construction Planner/Scheduler; Maintenance Planner, EIA XXI - Repsol, SKR01 SKSOL LUBE BASE OIL COMPLEX

START Date: 
September, 2012

Assigned to SKSOL, a joint venture of REPSOL S.A. (Spain) and SK Lubricants (Republic of Korea), to schedule the construction of a new lubricant plant, including two process units, an onsite tanks area and a seaside tanks area, reporting to the Organization Project Management Team

Assistant Construction Planner/Scheduler; Maintenance Planner, EIA XXI - Repsol, SKR01 SKSOL LUBE BASE OIL COMPLEX

START Date: 
September, 2012

Assigned to SKSOL, a joint venture of REPSOL S.A. (Spain) and SK Lubricants (Republic of Korea), to schedule the construction of a new lubricant plant, including two process units, an onsite tanks area and a seaside tanks area, reporting to the Organization Project Management Team

Assistant Construction Planner/Scheduler; Maintenance Planner, EIA XXI - Repsol, SKR01 SKSOL LUBE BASE OIL COMPLEX

START Date: 
September, 2012

Assigned to SKSOL, a joint venture of REPSOL S.A. (Spain) and SK Lubricants (Republic of Korea), to schedule the construction of a new lubricant plant, including two process units, an onsite tanks area and a seaside tanks area, reporting to the Organization Project Management Team

Construction Planner, AL Habtoor - Leighton Group, Iris Bay Tower

START Date: 
July, 2007

Project: Iris Bay Tower  
Briefing: 3B+GF+4P+36+Roof - Sh.Zayed road, Business Bay.
 
Job Description:  
• Preparation of the weekly, monthly and coordination meeting reports. • Updating the program as per the actual progress on site, and retrieve percentages of planned and actual progress.

• Developed Extension of Time Programs and Contract Documentation for claims as per project requirements.

• Instrumental in contract documentation related to contractual issues, claims, delays and impact analysis, etc.