Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

EVA

Project Planner, Xervon Palmers, Edinburgh Waverley Station Redevelopment

START Date: 
January, 2010
END Date: 
February, 2013

Initially employed as part of the National Bid Team responsible for developing Tender Programmes for various bids taking place across the UK.  Thereafter a part of the Edinburgh Waverley Station Redevelopment Project Controls Team responsible for monitoring and evaluating the earned value and productivity targets set in the client’s programmes.  Duties also included creating possession programmes for works taking place during rail track isolations and providing the Quantity Surveyors with the necessary information to assess the current/future position of the works to accurately pr

Senior Programme Planner, Network Rail Ltd, ERTMS

START Date: 
January, 2016

Senior Programme Planner – Major Programmes (Signalling)                                    

Assistant Planner or Planning Engineer, Costain, Thameslink - London Bridge Station Redevelopment

START Date: 
September, 2013
2013 – 2015 Current works – Costain - London Bridge Station Revelopment (as part of the Thames link programme worth £6.5 Billion): I currently work for Costain at London Bridge Station Redevelopment, since working here I have experienced planning for civil works undertaken by Costain (otherwise known as self-delivery works) and Early works such as demolition, piling and drainage (which have been part self-delivery and part subcontracted). I do both short term and long term planning.
Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
500

Assistant Planner or Planning Engineer, Costain, Thameslink - London Bridge Station Redevelopment

START Date: 
September, 2013
2013 – 2015 Current works – Costain - London Bridge Station Revelopment (as part of the Thames link programme worth £6.5 Billion): I currently work for Costain at London Bridge Station Redevelopment, since working here I have experienced planning for civil works undertaken by Costain (otherwise known as self-delivery works) and Early works such as demolition, piling and drainage (which have been part self-delivery and part subcontracted). I do both short term and long term planning.
Experience Hours (Planning & Scheduling): 
2000
Experience Hours (Cost Management): 
500
Experience Hours (Forensic Analysis): 
500

UK & Canada Planning Manager, Subsea 7, All UK & Canada Projects & Tenders

START Date: 
August, 2011
END Date: 
April, 2013

Line Management responsibility for twenty staff (at trainee, planner, senior & principle levels)
Redesign shape and personnel of planning department to meet current & future business requirements
Introduce, design & run new apprentice planner program
Raise profile of planning internally
Raise Client perception of planning competence
Produce and embed Standard Operating Procedure to planning
Produce and embed Planning Book of Knowledge for business

Experience Hours (Planning & Scheduling): 
3050
Experience Hours (Cost Management): 
1150

Senior Planner, Mott MacDonald Bentley, YW AMP5 Projects

START Date: 
June, 2010

I am currently the senior planner for Mott Macdonald Bentley working on all AMP5 schemes for Yorkshire water based in the Leeds office.  I also prepare tender submission programmes and have worked on multiple schemes for Severn Trent.  Prior to becoming a planner I have 10years of site experience from being an engineer through to site agent.  I have also gained commercial experience from being part of the estimating team.

I am an active member of the MMB BIM working group and have experience using a number of 4D planning software packages.

Experience Hours (Planning & Scheduling): 
6500

Planning / Project Manager, Crown House Technologies (Laing O'Rourke), Data Centres

START Date: 
September, 2007
END Date: 
February, 2009

Planning Manager, responsible for multiple tender proposals (both 1 and 2 stage) and on site projects. Working to develop practices to be adopted as company standards. Each project being High Value and Mission Critical.

Planning Manager, MACE GROUP LIMITED, Data Centres

START Date: 
June, 2011

Planning Manager, responsible for multiple tender proposals (both 1 and 2 stage) and on site projects. Working to develop practices to be adopted as company standards. Each project being High Value and Mission Critical.

Project Controls Lead Anayst, Black & Veatch, Various

START Date: 
November, 2011

Currently Working on the Yorkshire Water Large Contract Framework £10m +

Snr. Project Planning Engineer, Kaefer C&D Ltd, Ratcliffe REU & Asbesto's Removal Project

START Date: 
December, 2011

Responsible for the Planning of a Major upgrade at the Ratcliffe Power Station Uk, working as part of the kaefer C&D team to provide the service of: Access, Thermal Insulation, Industrial painting and Cleaning and Civil & Construction Works. I am responsible as Snr. Project Planner to schedule all relevent task and track progress and productivity.

As Part of this I am also the lead Planner of the removal of asbesto's material at Ratcliffe Power Station.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content