Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Risk Management

Project Planning and Control Manager, EWEN PMS, Portuguese High Speed Rail Link

START Date: 
July, 2011
END Date: 
December, 2012

Set-up of complete project schedule and cost control system for the High Speed Rail link in Portugal.

Senior Quantity Surveyor/Contract Administrator, RG Lagman and associates/NGB Construction/Cebarco-WCT Eng'g Berhad/Dhafir Dev't & Contracting/Faithful+Gould/GPD Investments LLC/Technologists Inc./AECOM, Civil (roads and bridges), formula 1 racing circuit

START Date: 
October, 1996
Quantity Surveying & Cost management: •Cost Estimation & Cost control, Contract Management, Procurement Coordination; •Prepare BOQ recapitulation; •Prepare Monthly Financial Affairs Report; •Prepare and Maintain Interim and Final Quantity Books; •Check the Contractor’s interim and final pay certificates; •Evaluate unit rates for new items of works; •Check joint measurements for interim payments; •Compute final pay quantities; •Maintain current as-built drawings as the work progresses; •Maintain progress schedule and cash flow chart; •Assist in preparation of Variation Orders. 
Experience Hours (Planning & Scheduling): 
5750
Experience Hours (Cost Management): 
28800

Current: VP Project Controls, AMEC Foster Wheeler, Lump Sum Design&Supply etc., Lump Sum Turn Key Projects

START Date: 
January, 2015
VP Project Controls with overall responsibility of Amec Foster Wheeler Energia Oy Group Project Controls activities (Project level: Cost, manhours&cash control, forecasting, reporting, project reviews, scheduling, progress evaluation, Earned Value) (Company level: project portfolio reporting, accrued profit/contract profit calculations and forecasting, company resource and manpower reporting and forecasting, various other analyses to support group senior management on business decisions) - Project Control global function leader at Power Systems & Technology Group (at global power group 'GPG')
Experience Hours (Planning & Scheduling): 
100
Experience Hours (Cost Management): 
100
Experience Hours (Forensic Analysis): 
3000

Technical Manager Project Controls, Kvaerner, Numerous Projects worldwide

START Date: 
July, 2010
END Date: 
July, 2012
  • Technical Manager responsible for support of proposals development and support in planning/scheduling, estimating and progress reporting for Business Development in Houston Texas. Implement and train personnel in planning and scheduling utilizing Primavera version 3 conversions to Primavera Version 6.
Experience Hours (Planning & Scheduling): 
5100
Experience Hours (Forensic Analysis): 
600

Vice President of International Operations, IMTC-MEI, Numerous Projects worldwide

START Date: 
August, 2007
END Date: 
March, 2010

From project Controls Manager to Vice President International operations responsible for all international projects in relations to business management, document control, planning, scheduling, cost control, risk management, estimating, business development, negotiations adn administration

Experience Hours (Planning & Scheduling): 
3400
Experience Hours (Forensic Analysis): 
1550

Project Services Manager, Conoco-Phillips, Naryan Mar Neftigaz Facility

START Date: 
April, 2006
END Date: 
July, 2007

Project Services Manager responsible for Dcoument Control, Contracts, Planning, Scheduling, Cost Control, Risk management, EVM, Change management and project reporting for a #3.5 billion oil refinery expansion, pipeline, and terminal facility

Experience Hours (Planning & Scheduling): 
1400
Experience Hours (Cost Management): 
400
Experience Hours (Forensic Analysis): 
600

Project Controls Manager, Parsons, Iraqi Water Restoration

START Date: 
January, 2006
END Date: 
May, 2006

Project Controls Manager on Water Restoration Project Baghdad Iraq responsible for project controls and transfer of technology

Experience Hours (Planning & Scheduling): 
650

Lead Planner and EVM Manager, KBR, Iraq oil Restoration

START Date: 
May, 2005
END Date: 
January, 2006

Change manegement, Earned Value Management and Lead Planning for Oil Restoration Project Basra Iraq

Experience Hours (Planning & Scheduling): 
2700
Experience Hours (Cost Management): 
750

Project Manager, Krump Construction, Tallac Zephyr Point Hotel and Conference Center

START Date: 
March, 2004
END Date: 
May, 2005

Project Manager performing all contracts, engineering and project controls for construction new hotel and conference center as well as renovations of a second hotel in Lake Tahoe.

Experience Hours (Planning & Scheduling): 
950
Experience Hours (Forensic Analysis): 
950

Project Controls Manager EMEA, Lucent, GSM - 3G

START Date: 
May, 1999
END Date: 
September, 1999

Planning, Scheduling, Cost Control, Change Management, Implementation and traing of Project Controlsd Systems and tools.

Experience Hours (Planning & Scheduling): 
400

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content