Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Civil (roads and bridges)

civil site eng. & planning eng., Shib Al Jazirah Contracting Company, Civil (roads and bridges)

START Date: 
January, 2009
END Date: 
September, 2015

Site Engineer-( January  2009 – September 2015)

 

Project Undertaken: Construction of North West Leg Project

Project Description: An all-new 13 Km. Multilane Dual Carriageway with Service Roads complete with Drainage System, Lighting, Traffic Signage, Vital Appurtenances, etc. The Project also includes seven Diamond Interchanges (pre-stress voided slabs) at major road crossings, and Three Long Wadi Bridges with more than 700 – 40 m. Pre-stress Beams (Wadi Hanifah, Wadi Mahadiyah, and Wadi Ubayer) having a combined length of 2 Km.

Experience Hours (Planning & Scheduling): 
16000
Experience Hours (Cost Management): 
16000

Civil Engineer/ Project Controls Manager, Fulton Hogan, Civil (roads and bridges)

START Date: 
September, 2015

Project controls - area wide manging 2 - 3 jobs

Experience Hours (Planning & Scheduling): 
200
Experience Hours (Cost Management): 
400
Experience Hours (Forensic Analysis): 
400

Civil Engineer-Scheduler & Cost Estimator, Fulton Hogan, Civil (roads and bridges)

START Date: 
November, 2014
END Date: 
June, 2015

Worked as estimator for a civil contractors - Porject ranging from 1m - 4m

Experience Hours (Planning & Scheduling): 
200
Experience Hours (Cost Management): 
0
Experience Hours (Forensic Analysis): 
400

Senior Planner (Project Management Consultant), Driver Trett, Civil (roads and bridges)

START Date: 
November, 2015
END Date: 
August, 2018

Working as Project Managment Consultant to the major Road project in the Sultanate of Oman.

Project: New Batinah Expressway

Construction of main carriageway, Interchanges, Wadi Bridges, Underpass Bridges, and Culverts.

Package 4 (KM 136+500 - KM 187+043)

Package 5 (KM 180+000 - KM 221+000)

Package 6 (KM 221+000 - KM 266+000)

Planning Engineer, STRABAG Oman LLC, Civil (roads and bridges)

START Date: 
June, 2008

Cuurently working as a planning engineer is STRABAG Oman LLC

Planning and Execution of infrastructure projects mainly Roads and Highway using project management tools Primavera 6.0 and MS Project.

Municipal Planning and Development Officer, Local Goverment Unit (LGU), , Civil (roads and bridges)

START Date: 
May, 1988
END Date: 
August, 1992

Tasked as local Government Department Head responsible for the administration of:

Civil Site Engineer, Afcons Infrastructure Limited, Civil (roads and bridges)

START Date: 
September, 2003
END Date: 
April, 2005

Responsibilities handled:

 

  • Involved in the execution of the various construction elements of bridges (piles, pile caps, piers, pier caps etc...)
  • Involved in the execution of approach road works to the bridges.
  • Coordination with Clients, Consultants & Sub-Contractors.
  • Preparation of Daily Activity Reports.
  • Preparation of actual progress of activities to given work schedule.
  • Preparation of monthly reconciliation statements of cement and steel.
  • Involved in ISO Works such as Documentati

PLANNING ENGINEER, JFN Contracting, Civil (roads and bridges)

START Date: 
May, 2012

Prepare project programme schedule for bidding purposes and for schedule and update.

Prepare monthly billing and document controlling works.

Civil Site Supervisor, (PMCJV) Pakistan Motorway Contractor Joint Venture., Civil (roads and bridges)

START Date: 
June, 2002
END Date: 
July, 2003

 

(PMCJV) Pakistan Motorway Contractor Joint Venture 2002 - 2003.

Responsibilities as Construction Supervisor:

 

·         Supervision of technical terms & checking of site works according to specifications & drawings.

·         Quality control of concrete casting, Formwork, Erection of Steel structure. Verification of concrete mix based on application.

Senior Quantity Surveyor/Contract Administrator, RG Lagman and associates/NGB Construction/Cebarco-WCT Eng'g Berhad/Dhafir Dev't & Contracting/Faithful+Gould/GPD Investments LLC/Technologists Inc./AECOM, Civil (roads and bridges), formula 1 racing circuit

START Date: 
October, 1996
Quantity Surveying & Cost management: •Cost Estimation & Cost control, Contract Management, Procurement Coordination; •Prepare BOQ recapitulation; •Prepare Monthly Financial Affairs Report; •Prepare and Maintain Interim and Final Quantity Books; •Check the Contractor’s interim and final pay certificates; •Evaluate unit rates for new items of works; •Check joint measurements for interim payments; •Compute final pay quantities; •Maintain current as-built drawings as the work progresses; •Maintain progress schedule and cash flow chart; •Assist in preparation of Variation Orders. 
Experience Hours (Planning & Scheduling): 
5750
Experience Hours (Cost Management): 
28800

Market Place

No results found... (try selecting a different content filter)

Syndicate content