Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Project Contorls; Cost Management; Project Planning; Progress Monitoring; Primavera P6; Project Coordinating; Change and Risk Management; Internal Systems and Procedure

Project Controls Engineer, Blackcat Engineering And Construction, Annual Maintenance Turnaround for Oryx GTL, Qatar Gas 3 & 4 Onshore Project, Qatar Petroleum, Shell GTL Project

START Date: 
January, 2014

ADevelop and update Work Breakdown Structure (WBS) and Cost Code of Accounts (CCA), project-specific Cost Control Procedures, Cost Breakdown Structure (CBS)

ACreate the Project First Budget from tender estimates and monitor the cost booking to respective Cost Centers

AEstablish the project controls function of for all projects in terms of planning/scheduling, cost estimating, cost budgeting, cost control, change management and progress and performance management.

Experience Hours (Planning & Scheduling): 
1150
Experience Hours (Cost Management): 
2300
Experience Hours (Forensic Analysis): 
1150

Market Place

No results found... (try selecting a different content filter)

Syndicate content