%100 Project Planning; Scheduling; Performance Monitoring

Planning Engineer, DEPA Interiors LLC , 5- Start Hotels , High End Multi purpose Buildings - Complete Fitout Scope

START Date: 
April, 2017
  • Monitoring and Tracking Site Progress
  • Assisting PMO in Forensic Delay Analysis
  • Implementation of EVM to monitor Project cost progress.
  • Oversee schedules and risk management plans and provide warnings hindering project results.
  • Maintain and validate project schedule information through regular collaboration with project staff.
Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
3000

Head of Planning & Scheduling, Al Geemi & Partners, •New Clusters / Service Buildings and Miscellaneous Facilities at Asab for ADCO, •Construction of Married Staff Accommodation, Facilities & Related Infrastructure at Ruwais for ADNOC, •Roads & Utility Wo

START Date: 
July, 2006
END Date: 
March, 2008
  • Evaluated & determined appropriate construction delivery systems and most cost-effective plan / schedule for completing the project
  • Created the manpower histogram & cash inflows to find out the resource availability and the different options to arrange the remaining resource
  • Tracked the different delay events and prepared the EOT claims, accordingly
  • Actively involved with their projects, as per the request from the ADNOC and ADCO managements
Experience Hours (Planning & Scheduling): 
3400

Lead Planner - Offshore Works, PT. Gunanusa Fabricator, Yadana Subsidence Project EPSCC-1 and EPSC-2

START Date: 
August, 2012
END Date: 
March, 2014

• Review contractors project schedule and prepare join schedule of contractor work.
• Monitor and analyze ongoing construction offshore schedule and advice works priority.
• Prepare and monitor status of variation works.
• Coordinate with Construction and Operation to maintain the target schedule as Contractor 3 week look ahead plan.
• Intergrate the Fabrication planning with the Offshore work planning.
• Coordinate with Engineering team to accommodate input from Engineering task sheet.

Experience Hours (Planning & Scheduling): 
10500
Experience Hours (Forensic Analysis): 
8100