Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Lead Planner - Offshore Works

Lead Planner - Offshore Works, PT. Gunanusa Fabricator, Yadana Subsidence Project EPSCC-1 and EPSC-2

START Date: 
August, 2012
END Date: 
March, 2014

• Review contractors project schedule and prepare join schedule of contractor work.
• Monitor and analyze ongoing construction offshore schedule and advice works priority.
• Prepare and monitor status of variation works.
• Coordinate with Construction and Operation to maintain the target schedule as Contractor 3 week look ahead plan.
• Intergrate the Fabrication planning with the Offshore work planning.
• Coordinate with Engineering team to accommodate input from Engineering task sheet.

Experience Hours (Planning & Scheduling): 
10500
Experience Hours (Forensic Analysis): 
8100

Lead Planner - Offshore Works, KCA Deutag, Offshore Drilling oil and Gas Projects

START Date: 
January, 2014
END Date: 
March, 2015

RDS (A division of KCA DEUTAG Drilling Ltd)

Johan Sverdrup (Statoil) – FEED: Project Value – 14 BUSD

Drilling Platform Lead Planner – London, UK

Lead Planner - Offshore Works, BECHTEL, Hay Point Expansion Phase 3

START Date: 
May, 2011
END Date: 
June, 2014
  • Schedule Management
    • Review sub-contactor network program
    • Identify Logic and duration issues
    • Identify interfaces with other contractors and its impact
    • Identify engineering deliverables issues and its impacts with procurement and construction
    • Identify material delivery issues and its impacts with construction
  • Resource management
    • Review sub-contractor resource plan
    • Identify major issues with resource availability
    • Review sub-contactor's Plant and equipment plan
  • Earned Value mana
Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
950
Experience Hours (Forensic Analysis): 
1000

Market Place

No results found... (try selecting a different content filter)

Syndicate content