Planning Engineer, DEPA Interiors LLC , 5- Start Hotels , High End Multi purpose Buildings - Complete Fitout Scope

START Date: 
April, 2017
  • Monitoring and Tracking Site Progress
  • Assisting PMO in Forensic Delay Analysis
  • Implementation of EVM to monitor Project cost progress.
  • Oversee schedules and risk management plans and provide warnings hindering project results.
  • Maintain and validate project schedule information through regular collaboration with project staff. Responsible for overall project coordination and progress evaluation.
  • Using critical path analysis and identifying delays, preparing revised programs and recovery plans as per project requirements.
  • Preparing the detailed program of works for all the Sub-cons working on the project.
  • Evaluating the work progress of sub-contractors with timely intimation about the delays.
Experience Hours (Planning & Scheduling): 
4000
Experience Hours (Cost Management): 
1000
Experience Hours (Forensic Analysis): 
3000