Western Australia (OC.AU.WA)

Project Controls Planner, Monadelphous Engineering Associates, Cape Lambert 353

START Date: 
October, 2011
END Date: 
May, 2014

Tender Submission and Project Controls Planner, Monadelphous, Perth

Project Planner, Monadelphous, Cape Lambert

Experience Hours (Planning & Scheduling): 
6650
Experience Hours (Cost Management): 
400
Experience Hours (Forensic Analysis): 
0

Raf Many

First Name: 
Raf
Last Name: 
Many
Professional Since: 
Feb-2000 (24.8 yrs experience)
Years Experience: 
0

Projects Planner, John Holland Group, Devils Creek Gas Project

START Date: 
July, 2009
END Date: 
August, 2009

Devils Creek Gas Project AU$520 MillionGreenfields Onshore Gas Treatment/Dehydration Plant.

Projects Planner, (Specific Assignment), 07/2009 to 08/2009

Integrate Clough design and Bill of quantities data into John Holland/Leighton’s CATS estimating system and convert CATS estimating system into Primavera schedule for tender in such a manner that the estimate and schedule balance by area, units of measure and cost.

Experience Hours (Planning & Scheduling): 
300

Forensic Planner / Delay Analyst, Fortescue Metals Group, T155 Jetty Project

START Date: 
March, 2012
END Date: 
May, 2012

T155 Jetty Project – 305 Tonne Jetty Improvement Project.

Forensic Planner, (Specific Assignment), 03/2012 to 05/2012

Defense review for owner against Jetty Construction contractor EOT claim

Forensic Planner, Brookfield Multiplex, Maundering Weir Water Treatment Plant Project

START Date: 
February, 2012
END Date: 
June, 2012

Maundering Weir Water Treatment Plant – 165,000 Cubic Meters of water per day Water Treatment Plant.

Forensic Planner, (Specific Assignment), 02/2012 to 06/2012

Integrate Bill of Quantity data to progress schedules to assist client in development of Extension of Time claim case due to large change in scope and delay in design

Experience Hours (Forensic Analysis): 
750

Forensic Planner, CTEC, Merredin Power Station Project

START Date: 
July, 2012
END Date: 
September, 2012

Merredin Power Station Project. 82MW PowerStation Project in Western Australia.

Forensic Planner, (Specific Assignment – Part time consulting role)07/2012 to 09/2012

Defense EOT claim preparation for client against contractor due to late delivery of equipment

Experience Hours (Forensic Analysis): 
200

Forensic Planner, Ertech, Marandoo Dewatering Project

START Date: 
June, 2013
END Date: 
March, 2014

Marandoo Dewatering Project – 24km pipeline with 27 bore pumps, Transfer & booster pump stations in Western Australia.

Forensic Planner, (Specific Assignment) 06/2013 to 03/2014

Preparation of Extension of time claim and support in Mediation process and conclusion

Experience Hours (Forensic Analysis): 
1250

Forensic Planner, Ertech, Chevron Wheatstone Project

START Date: 
January, 2014
END Date: 
March, 2014

wheatstone villageChevron Wheatstone Construction Village Buildings & utilities Project. Western Australia.

Forensic Planner, (Specific Assignment), 01/2014 to 03/2014

Preparation of Extension of time claim schedule in “Impacted as Planned” format.

Experience Hours (Forensic Analysis): 
150

Forensic Planner, PIHA, RIO-TINTO Cape Lambert Expansion Project

START Date: 
August, 2013
END Date: 
June, 2014

RIO-TINTO Cape Lambert Services Contract Construction Project of Piping and Cable infrastructure at Point Sampson in Western Australia.

Forensic Planner, (Specific Assignment), 08/2013 to 06/2014

Preparation of Extension of time claim and support in Mediation process and conclusion

Experience Hours (Forensic Analysis): 
600

Principle Projects Planner, Newcrest Mining Limited, TELFER PROJECT

START Date: 
December, 2003
END Date: 
December, 2008

Principle Projects Planner, 12/2003 to 12/2008 Telfer ProjectAU$560 Million Open Pit and Underground project with Concentrator treating 20 million tonne per annum gold and copper concentrate plant, in Western Australia.

Experience Hours (Planning & Scheduling): 
9100
Experience Hours (Cost Management): 
600
Experience Hours (Forensic Analysis): 
200