Claims review/build/analyze

Forensic Planner, Brookfield Multiplex, Maundering Weir Water Treatment Plant Project

START Date: 
February, 2012
END Date: 
June, 2012

Maundering Weir Water Treatment Plant – 165,000 Cubic Meters of water per day Water Treatment Plant.

Forensic Planner, (Specific Assignment), 02/2012 to 06/2012

Integrate Bill of Quantity data to progress schedules to assist client in development of Extension of Time claim case due to large change in scope and delay in design

Experience Hours (Forensic Analysis): 
750

Forensic Planner, Ertech, Marandoo Dewatering Project

START Date: 
June, 2013
END Date: 
March, 2014

Marandoo Dewatering Project – 24km pipeline with 27 bore pumps, Transfer & booster pump stations in Western Australia.

Forensic Planner, (Specific Assignment) 06/2013 to 03/2014

Preparation of Extension of time claim and support in Mediation process and conclusion

Experience Hours (Forensic Analysis): 
1250

Forensic Planner, Ertech, Chevron Wheatstone Project

START Date: 
January, 2014
END Date: 
March, 2014

wheatstone villageChevron Wheatstone Construction Village Buildings & utilities Project. Western Australia.

Forensic Planner, (Specific Assignment), 01/2014 to 03/2014

Preparation of Extension of time claim schedule in “Impacted as Planned” format.

Experience Hours (Forensic Analysis): 
150

Forensic Planner, PIHA, RIO-TINTO Cape Lambert Expansion Project

START Date: 
August, 2013
END Date: 
June, 2014

RIO-TINTO Cape Lambert Services Contract Construction Project of Piping and Cable infrastructure at Point Sampson in Western Australia.

Forensic Planner, (Specific Assignment), 08/2013 to 06/2014

Preparation of Extension of time claim and support in Mediation process and conclusion

Experience Hours (Forensic Analysis): 
600