Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

West Coast Mainline

Project Planner, Network Rail UK, West Coast Mainline

START Date: 
January, 2008

I’m competent in developing and maintaining a detailed resource loaded schedule

 -developing the schedule in an agreed [WBS] work breakdown structure

-Activity coding

-resource loading

-cost loading

I assign resources and costs to activities {SPI & CPI}

I Set baselines and milestones to compare progress against

I Record actual progress against the baselines and making amendments where necessary [updating]

I create a 4 week look ahead [project plan forecast]

Planner , Network Rail, West Coast Mainline

START Date: 
January, 2005
END Date: 
November, 2002

Responsible for the establishment and maintenance of project schedules for the Linespeed Enhancements, FTN, Civils, Plant & Machinery and Structures disciplines of the multi-million pound WCML contract. This involved long term planning of the works, identification of Key Milestones from Concept to Handback, activity logic and durations as well as the day to day management of the project schedules. Attendance at Progress Meetings with contractors and analysis of their programmes to capture progress and forecast.

Planning & Resource Co-ordinator, Network Rail, West Coast Mainline

START Date: 
August, 2002
END Date: 
July, 2007

After 5 years working as a metalurgist in Australian Nickel and Cobalt refining I moved to UK.

I worked for Carillion Rail and then Network Rail as Assistant Rail Manager and then Planniong and Resource co-ordinator helping found the WCML On track machine group.

Experience Hours (Planning & Scheduling): 
8000
Experience Hours (Cost Management): 
2000

Market Place

No results found... (try selecting a different content filter)

Syndicate content