Website Upgrade Incoming - we're working on a new look (and speed!) standby while we finalise the project

Turkey

Simultaneous Translator, Gama Industries, Cement Factory Construction, Ankara, Turkey

START Date: 
June, 1992
END Date: 
July, 1992

Simultaneous Translator.

I was the simultaneous translator for two Frenchmen temporarily assigned to supervise the first ever locally constructed rotary oven of a cement factory in Ankara.

Simultaneous translation basically between French & Turkish with management and workers and French and English when English speakers connected with the Frenchmen.

This got me interested in Industrial Projects. :)

Acting Control Engineer, Atilla Doğan A.Ş., Natural Gas Network Installation Project, Ankara, Turkey

START Date: 
May, 1996
END Date: 
August, 1997
1996 – 1997 (Summer break) Atilla Doğan A.Ş. Ankara/TURKEYInternship, acting Control Engineer for the client. (Quality control of subcontractors work for a duration of 13 weeks)Project details: Work consisted of the installation of underground urban natural gas lines throughout the city of Ankara /Turkey (central lines including thousands of building connections).

Technical Office Engineer, Planning, Cost Control, Atilla İnş. Tur. ve Tic. A.Ş., Multiple (9) Projects, Ankara, Turkey

START Date: 
April, 2001
END Date: 
January, 2003

Technical Office. Infrastructure work monthly due reports(İller Bank), Biding Dossiers, Price Assessments.

Project details:Works consisting of the construction of the foul water and rainwater systems for various small cities.

●      Monthly due reports for various construction sites (nine sites at peak, minimum 5 sites).

●      Follow-up (seek approval) on location of two site due reports with client.

Technical Office Manager, ÇEL-AT Joint Venture, Burkan-4, Bursa, Turkey

START Date: 
January, 2003
END Date: 
January, 2004

Technical Office. Payment Certificates of client and subcontractors, Price Assessments, Cost Control.

Project details:Scope contract value US$4,000,000. Works consisting of the construction of the foul water and rainwater system for sections of the Bursa city.

●      Due reports to client and subcontractors,

●      Draftsman for company letters to be sent to client.

Technical Office Engineer, Planning & Cost Control, Alsim Alarko, Baku-Tiblisi-Ceyhan Crude Oil Pipeline, Erzincan, Turkey

START Date: 
June, 2004
END Date: 
December, 2004

Technical Office. Planning, payment certificates of client and subcontractors, cost control (6 months).

Project details:Project value US$4Billion, scope contract value US$30,000,000. Scope pipeline total length is 387(470)km and is of 42’’ steel pipes.

●      Company master Primavera scheduler.

●      Progress reporting.

Market Place

No results found... (try selecting a different content filter)

Syndicate content