Technical Office Engineer, Planning & Cost Control, Alsim Alarko, Baku-Tiblisi-Ceyhan Crude Oil Pipeline, Erzincan, Turkey
START Date:
June, 2004
END Date:
December, 2004 Technical Office. Planning, payment certificates of client and subcontractors, cost control (6 months).
Project details:Project value US$4Billion, scope contract value US$30,000,000. Scope pipeline total length is 387(470)km and is of 42’’ steel pipes.
● Company master Primavera scheduler.
● Progress reporting.