Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

Tanjung

Senior Planning & Schedule Engineer, PT. Punj Lloyd Indonesia, 2x30MW Coal Fired Power Plant, Tanjung, Tabalong – Kalimantan Selatan, Indonesia.

START Date: 
November, 2009
END Date: 
April, 2010
  1. Create, maintain and updating Master Schedule (using Primavera Version 5).
  2. Create Two Weeks Look Ahead Schedule in level 5.
  3. Review Sub-Contractor schedule and progress and ensure the progress of Sub-Contractor is correct.
  4. CPM analysis.
  5. Oversee any possible delay of work and prepare catch up plan.
  6. Studied the possibilities of delays in the work and proposed solutions to overcome these delays.
  7. Plan allocation of labor and equipment and compare with actual conditions in the site.
  8. Make a budget plan using Primavera P5

Market Place

No results found... (try selecting a different content filter)

Syndicate content