PT. Punj Lloyd Indonesia

SENIOR PLANNER, PT. Punj Lloyd Indonesia, %26 Oil %26 Gas Projects

START Date: 
November, 2015
END Date: 
July, 2017

fdsff sdgdf hfdfej fiSF SJDIjd ihu hdwJD FJWU IDH IWKF KHWU DGQWID JLQW MDK SDWF

Experience Hours (Planning & Scheduling): 
200
Experience Hours (Cost Management): 
300
Experience Hours (Forensic Analysis): 
250

Senior Planning & Schedule Engineer, PT. Punj Lloyd Indonesia, 2x30MW Coal Fired Power Plant, Tanjung, Tabalong – Kalimantan Selatan, Indonesia.

START Date: 
November, 2009
END Date: 
April, 2010
  1. Create, maintain and updating Master Schedule (using Primavera Version 5).
  2. Create Two Weeks Look Ahead Schedule in level 5.
  3. Review Sub-Contractor schedule and progress and ensure the progress of Sub-Contractor is correct.
  4. CPM analysis.
  5. Oversee any possible delay of work and prepare catch up plan.
  6. Studied the possibilities of delays in the work and proposed solutions to overcome these delays.
  7. Plan allocation of labor and equipment and compare with actual conditions in the site.
  8. Make a budget plan using Primavera P5