Shell`s Pearl GTL Project

Planning Engineer, Descon Engineering, Shell`s Pearl GTL Project

START Date: 
February, 2007
END Date: 
February, 2008

MAIN RESPONSIBILITIES

Reporting to the Planning Manager, my role as Planning Engineer involves the following activities

-       Verification of Scope of Work for the Project and definition of Standard Man-hours against each Cost Center

-       Development of Level IV plan in P3(approx. 3000 Activities)

Experience Hours (Planning & Scheduling): 
2000