Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Plant Planning & Schedule Control Expert, GS Engineering & Construction Corp. (GS E&C), KOC Elevated Substations Project – South & East of KUWAIT and Rabigh II Refining and Petrochemical Project – Rabigh, Saudi Arabia

START Date: 
September, 2011

 

GS Engineering & Construction Corp. (GS E&C)

September 2011 – Present                                                                                            

      Plant Planning & Schedule Control Expert                     Seoul, SOUTH KOREA

 

 

KOC Elevated Substations Project – South & East of KUWAIT

Acting as the proposal team member in bidding phase including:

  • Preparation of contractual requirements of planning and scheduling parts of proposal;
  • Preparation of Level I, II and III Schedule for EPCC parts of project.

Rabigh II Refining and Petrochemical Project – Rabigh, SAUDI ARABIA

The extension of Rabigh Petrochemical Plant in Rabigh city with initial value of 1.7 billion US$ awarded to GS E&C for completion of EPCC parts of project in CP3, CP4 and UO1 packages;

Acting as the project planner, scheduler and control expert including:

  • Defining scope of work;
  • Preparation of WBS of project;
  • Preparation of Planning & Scheduling procedures including Progress Measurement System;
  • Estimating time and development of Level II and III of schedule;
  • Controlling the project using Earned Value Management and In-House management software named SITS (Schedule Information Tracking System).