Site Cost Lead, Tecnicas Reunidas, LNG Seagas Damietta (Egypt)

START Date: 
July, 2003
END Date: 
September, 2004

I worked as the LSTK EPC contractor for construction of LNG Train in Damietta, Egypt.  Project was a JV of KBR, JGC, Tecnicas Reunidas, and M.W. Kellogg. This project was extremely schedule driven, and the challenge was to reduce project costs without impacting the overall progress.  I did this through rigorous change management, detailed cost control down to WBS+5 level, and a very indepth manpower plan to ensure the right mix of talent stayed on the project.

Experience Hours (Planning & Scheduling): 
0
Experience Hours (Cost Management): 
2000
Experience Hours (Forensic Analysis): 
0

SENIOR PLANNING ENGINEER , TECNICAS REUNIDAS, KBR, JGC, LNG Seagas Damietta (Egypt), joint venture of KBR (Kellogg, Brwon & root)-TRSA (Tecnicas Reunidas)-JGC (Japan Gas Company)

START Date: 
May, 2001
END Date: 
February, 2003

EPC planning of the LNG Sea Gas Project Plant of Damietta (Egypt), joint venture of KBR (Kellogg, Brwon & root)-TRSA (Tecnicas Reunidas)-JGC (Japan Gas Company) with an investment budget of 1,2 billion USD under the TKLSP contract terms.

The project specification required the development of design, procurement and contruction phases of a LNG plant, four LNG ship carriers of 150.000 TPM each to be be built in Korea, and two LNG tanks of 150.000 M3 as the LNG storage system.

This EPCC project was a managing joint venture composed by three engineering companies, KBR-

SENIOR PLANNING ENGINEER , TECNICAS RENUDIDAS, KBR, JGC, LNG Seagas Damietta (Egypt), joint venture of KBR (Kellogg, Brwon & root)-TRSA (Tecnicas Reunidas)-JGC (Japan Gas Company)

START Date: 
May, 2001
END Date: 
February, 2003

EPC planning of the LNG Sea Gas Project Plant of Damietta (Egypt), joint venture of KBR (Kellogg, Brwon & root)-TRSA (Tecnicas Reunidas)-JGC (Japan Gas Company) with an investment budget of 1,2 billion USD under the TKLSP contract terms.

The project specification required the development of design, procurement and contruction phases of a LNG plant, four LNG ship carriers of 150.000 TPM each to be be built in Korea, and two LNG tanks of 150.000 M3 as the LNG storage system.

This EPCC project was a managing joint venture composed by three engineering companies, KBR-