Website Upgrade Incoming - we're working on a new look (and speed!) standby while we deliver the project

2010 Inplot Mini Shutdown

Shutdown/Project Scheduler, Shell Refining Co. Fom. Bhd, 2010 Inplot Mini Shutdown, 2011 Major Turnaround, 2011 MAB Pit Stop Shutdown

START Date: 
June, 2009

Current Role:

  • - Responsible in Planning/Schedule Development stage for Shutdown/Turnaround
  • - Develop Integrated Execution Schedule – Structure
  • - Develop Code Structure in P3E as per system - Systemisation Structure
  • - Data entry / import of detail job plans and estimates into scheduling tool.
  • - Create logical network of activities and, ultimately, a critical path of work and schedule, without overly constraining the schedule.
  • - Updates schedule as required – typically daily or shiftly - based on planner reporte

Market Place

No results found... (try selecting a different content filter)

Syndicate content